Thursday, 11 June 2015

ISB-RWP Metro Bus Project Bidding Status

Bidding Status of Rawalpindi-Islamabad Metro Bus Project

BIDDING STATUS (RAWALPINDI) PACKAGE-I
Sr.#Name of PQ FirmEstimated Cost (Rs.)Bid Cost (Rs.)Above / BelowRank
 1M/s Z.K.B.5,319,960,7114,701,404,01711.63% Below1st
 2M/s Limak-Reliable (JV)
4,840,895,76210.19% Below2nd
 3M/s N.L.C.
5,050,000,0005.58% Below3rd
 4M/s Habib Construction Services5,069,317,4764.30% Below4th
 5M/s MAL-CALSONS (JV)5,422,136,0252.02% Above5th
 6M/s Technical Associates5,661,447,0906.74% Above6th
 7M/s F.W.O.5,829,809,3349.40% Above7th
 8M/s CRFG-HRL (JV)Not Participated in Bidding
 9M/s ZKB-UsmaniBidding documents not purchased

Top
Bidding Status (Rawalpindi) Package-II
Sr.#Name of PQ FirmEstimated Cost (Rs.)Bid Cost (Rs.)Above / BelowRank
 1M/s N.L.C.4,506,841,9724,484,833,3390.49% Below1st
 2M/s Technical Associates4,608,498,9312.26% Above2nd
 3M/s MAL-CALSONS4,666,386,6443.54% Above3rd
 4M/s Habib Construction Services4,697,925,3184.24% Above4th
 5M/s F.W.O.5,119,348,82913.59% Above5th
 6M/s ZKBThe Bid was returned unopened as M/s ZKB was lowest in Package-I
 7M/s Limak-Reliable (JV)Bidding documents not purchased
 8M/s CRFG-HRL(JV)Not Participated in bidding
 9M/s ZKB-Usmani (JV)The Bid was returned unopened as M/s ZKB was lowest in Package-I

Top
Bidding Status (Rawalpindi) Package-III
Sr.#Name of PQ FirmEstimated Cost (Rs.)Bid Cost (Rs.)Above / BelowRank
 1M/s Limak-Reliable (JV)3,938,255,0983,500,879,84211.11% Below1st
 2M/s MAL-CALSONS3,779,846,8774.02% Below2nd
 3M/s F.W.O.3,925,520,4820.32% Below3rd
 4M/s Habib Construction Services3,700,914,9076.03% Above4th
 5M/s Technical Associates4,223,116,7827.23% Above5th
 6M/s NLCThe Bid was returned unopened as M/s NLC was lowest in Package-II
 7M/s ZKBThe Bid was returned unopened as M/s ZKB was lowest in Package-I
 8M/s CRFG-HRL (JV)Not Participated in bidding
 9M/s ZKB-Usmani
Bidding documents not purchased

Top
 Summary Rawalpindi Part
RAWALPINDI PARTA.A CostEstimated CostTendered CostSaving
Package I (Flashman Hotel to Committee Chowk)5.675.314.700.61
Package II (Committee Chowk to 6th Road)4.934.504.480.02
Package III (6th Road to I.J.P Road)4.463.933.500.43
Land Acquisition & Shifting of Utilities2.82---
Escalators, Elevators & PSD Plat Forms1.59---
Total19.4713.7412.681.06 (7.71%)

Top

BIDDING STATUS ISLAMABAD PART

BIDDING STATUS (ISLAMABAD PART) PACKAGE-I
Sr.#Name of PQ FirmEstimated Cost (Rs.)Bid Cost (Rs.)Above / BelowRank
 1M/s Habib Construction Services.3,680,719,5563,354,331,3848.87% Below1st
 2M/s Limak-Reliable (JV)3,361,293,4978.68% Below2nd
 3M/s CWE-Sarwar (JV)
3,482,822,7355.38% Below3rd
 4M/s MAL-CALSONS
3,496,951,2044.99% Below4th
 5M/s CRFG-HRL-Matracon (JV)3,547,558,4953.62% Below5th
 6M/s F.W.O.
3,911,851,4956.28% Above6th
 7
M/s ZKBBid was rejected as was not accompanied with Bid Security
Not Participated in Bidding
 8M/S MAAKSONS
 9M/s N.L.CThe Bid was returned unopened as M/s NLC was lowest in Package-II

Top

BIDDING STATUS (ISLAMABAD PART) PACKAGE-II
Sr.#Name of PQ FirmEstimated Cost (Rs.)Bid Cost (Rs.)Above / BelowRank
 1M/s N.L.C.6,197,419,3905,567,141,48710.17% Below1st
 2M/s Habib Construction Services
5,592,132,3979.77% Below2nd
 3M/s Z.K.B-Usmani (JV)5,627,812,3729.19% Below3rd
 4M/s MAL-CALSONS5,786,417,2556.63% Below4th
 5M/s F.W.O.6,885,090,29911.10% Above5th
 6M/s CRFG-HRL (JV)Bidding documents not purchased

Top

BIDDING STATUS (ISLAMABAD PART) PACKAGE-III
Sr.#Name of PQ FirmEstimated Cost (Rs.)Bid Cost (Rs.)Above / BelowRank
 1M/s MAL-CALSONS3,126,545,8672,831,280,0679.44% Below1st
 2M/s Limak-Reliable (JV)2,894,173,8327.43% Below2nd
 3M/s ZKB2,962,511,9335.25% Below3rd
3,013,218,0273.62% Below4th
 4M/s CRFG-HRL-Matracon (JV)
3,337,949,1186.76% Above5th
 5M/s F.W.O.
 6M/s CWE-Sarwar (JV)3,413,913,0079.19% Above6th
 7M/S MAAKSONSNot Participated in Bidding
 8
M/s N.L.CThe Bid was returned unopened as M/s NLC was lowest in Package-II
The Bid was returned unopened as M/s Habib Construction Services was lowest in Package-I
10. M/s Habib Construction Services

Top

BIDDING STATUS (ISLAMABAD PART) PACKAGE-IV
Sr.#Name of PQ FirmEstimated Cost (Rs.)Bid Cost (Rs.)Above / BelowRank
 1M/s ZKB3,026,790,4232,868,503,7005.23% Below1st
 2M/sCRFG-HRL-Matracon (JV)2,874,698,6545.02%Below2nd
 3M/s F.W.O.2,971,882,1841.81%Below3rd
 4M/s CWE-Sarwar (JV)Not Participated in Bidding
 5M/S MAAKSONS           Not Participated in Bidding


Top
ELEVATORS

Sr.#Name of PQ FirmEstimated Cost (Rs.) Without dutiesBid Cost (Rs.)Above / BelowRankManufacturer
 1M/s Merin (Pvt.) Ltd645,000,000438,600,00032%Below1stSchindler(China)
 2M/s Ziafco Engineers & Contractors457,209,37829% Below2ndSigma by Otis(China)
 3M/SJeewajee-Qavi Engineering (JV)474,257,34026%Below3rdMitsubishi   Shanghai (China)
 4M/s Islamabad Industries & Trading Corporation497,777,78623% Below4thHyundai(China)
 5M/S Capital Strategies Group- Zealcon Engineering (JV)749,993,87716% Above5thThyssenKrupp (Spain)
 6M/s. Mark Development EMFORE Corporation (JV)Not participatedin Bidding

Top
 ESCALATORS

Sr.#Name of PQ FirmEstimated Cost (Rs.)(Without duties)Bid Cost (Rs.)Above / BelowRankManufacturer
 1M/s Merin (Pvt.) Ltd1,143,000,000829,200,00027%Below1stSchindler(China)
 2
M/s Jeewajee-Qavi Engineering (JV)918,000,00020%Below2ndMitsubishi Shanghai (China)
 3
M/s. Mark Development – EMFORE Corporation (JV)Not participatedin Bidding

Top
PLATFORM SCREEN DOORS (PSD)

Sr.#Name of PQ FirmEstimated Cost (Rs.) without dutiesBid Cost (Rs.)Above / BelowRankManufacturer
 1M/s MESSI Enterprises372,430,000341,246,96012.99%Below1stManusa(Spain)
2
M/s Pak German-Saddat Rashid (JV)392,172,9005.30%Above2ndAdis(Australia)

Top

PMA COMMAND & CONTROL CENTER

Sr.#Name of PQ FirmEstimated Cost (Rs.)Bid Cost (Rs.)Above / BelowRank
 1M/s DINSOSN416,974,630403,187,7143.31% Below1st
1497,862,22319.40% Above2nd
 2M/s Salman Enterprises
 3M/s Gulzari Associates
512,021,52122.79% Above3rd
560,122,62634.33% Above4th
 4M/s AmmantHussain & Co.
 5M/s Zahir Khan & BrothersBidding documents not purchased
 6M/s United Engineers & ContractorsBidding documents not purchased